Showing posts with label Camera Cable. Show all posts
Showing posts with label Camera Cable. Show all posts

Saturday, March 16, 2024

How to Splice Security Camera Wires

How to Splice Security Camera Wires

Splicing cables or wires is the act of combining two wires together, and it’s an indispensable skill for someone who owns or manages properties that use security cameras. You might need to do this to repair wires, lengthen wires, or combine two different wires together. 

There are two main types of security camera wires: ethernet cables and RG59 cables. Even an amateur can learn how to splice either type, and the process is relatively simple once you get some practice under your belt. 

Here, we’ll show you how to splice both ethernet and RG59 cables.

Can I Splice Security Camera Wires? 

By following simple instructions and tutorials, most people can splice security camera wires themselves. You’ll need some simple tools, such as wire cutters, wire strippers, electrical tape, and heat shrink tubing. Depending on how your wires are set up, you might also be able to splice wires together using a coupler, which makes the job even easier. 

It’s also important to note that while you can splice security camera wires together, that doesn’t always mean you should. Splicing cables could decrease the quality of your security footage, so when possible, it might be a better idea to run a new continuous cable. 

How Do You Splice Security Camera Wires? 

Before you can begin splicing your security camera wires, you need to know what type of wires you’re working with. 

If you have an IP security camera system, you’re likely working with Cat5 or Cat6 ethernet cables. These cables will consist of four twisted wire pairs encased in insulation. 

If you have a CCTV security camera system, you’re likely working with RG59 cables. This is an older type of cable, but it’s still used in many buildings. These cables will consist of copper wire encased in various layers of insulation and shielding. 

The Easiest Method for Splicing Security Camera Wires

Before you begin splicing, take a look at your wires. If they already have connectors on the ends, you’re in luck. Both ethernet cables and RG59 cables might already have connectors on the ends, and in that case, it’s easy to splice the cables. 

Simply find a compatible coupler and either insert or screw the ends of the cables into the coupler. With RG59 cables, it’s a good idea to wrap the connection with electrical tape after you’re done connecting the two cables.

How to Splice Security Camera Wires 

If your cables don’t already have connectors attached, you can still splice the wires together, but it will be a bit more complicated. The process will be different depending on whether you have ethernet cables or RG59 cables.

Splicing Security Camera Wires with Ethernet Cables 

Ethernet cables consist of small, fine wires, so it’s important to be very gentle and intentional when working with these wires. Follow these steps to splice ethernet security camera cables:

  1. First, use wire strippers to remove the outer insulation, which looks like a plastic coating on each wire you need to splice. Make sure you leave enough wire exposed to work with. 
  2. Put heat shrink tubing on only one of the wires. You’ll need this later when you’re finishing up. 
  3. Expose the inner core of each of the eight inner wires by carefully stripping off the outer layer. You’ll want to expose about a half inch of wire so you have enough to work with. Repeat this on each cable you need to splice.
  4. Combine each of the eight wires individually using a butt crimp. 
  5. Tape each of the eight connections with electrical tape. This helps strengthen the connection you’ve made. 
  6. Before sealing up your cables, it’s a good idea to test the connection to make sure it works. 
  7. When you’re done combining each wire, cover all of the connections with your heat shrink tubing. Use a heat gun to activate and shrink your tubing. 

When you’re finished, you should have a working ethernet cable. 

Splicing Security Camera Wires with RG59 Cables 

You’ll follow a relatively similar process when you splice RG59 cables. The main differences are the number of layers you need to work through and the number of wires you need to splice. Follow these steps to splice RG59 security camera cables: 

1.   Use wire strippers to remove the outer insulation on each end you need to splice. This will look like a plastic coating. Make sure you leave enough wire exposed to work with. 

2.   Put heat shrink tubing on only one of the cables. You’ll need this later when you’re finishing up. 

3.   Pull back the braided mesh, which is the next layer you’ll find in an RG59 cable.

4.   Cut and strip back the shielding and additional insulation layer; these are the next two layers you’ll find before you get to the wire. When removing these last two layers, be careful not to cut too deeply so you don’t damage the core. 

5.   Add another piece of heat shrink tubing that you’ll use once you have your connection made. 

6.   Use a butt crimp to connect the core on each end. 

7.   Wrap your connection with electrical tape. 

8.   Put the heat shrink tubing over your connection. Use a heat gun to activate and shrink your tubing. 

9.   Put a larger butt crimp over the braided mesh. 

10.Pull the heat shrink tubing over this connection. Again, use a heat gun to activate and shrink your tubing. 

11.Wrap your connection in electrical tape again. 

Depending on the type of cable you’re working with, you might have additional wires to connect when you get to the core. Some cables have additional wires for sound and to power a tilt and pan camera. If you find additional wires in the middle, follow the same process to connect those wires. 

When you’re finished, you should have a single working RG59 cable.

Why Do You Need To Splice Security Camera Wires? 

It might seem like quite a hassle to splice security camera wires, and it definitely takes time and effort. However, it’s good to know what to do in case you have a break in your wires and need to repair them quickly to get your security cameras back up and running. 

You also might need to splice wires to lengthen a cable, move a camera, or add additional security cameras. A good splice job can save you from needing to buy new cables.


Thursday, February 15, 2024

METHOD STATEMENT FOR PVC CONDUITS INSTALLATION

METHOD STATEMENT FOR PVC  CONDUITS  INSTALLATION



Ø TABLE OF CONTENTS

1. SCOPE

2. definitions

3. HEALTH  AND  SAFETY

4. OPERATION

5. installation  and  fixation

6. RESPONSIBILITIES

7. MANPOWER  REQUIRED

8. MATERIALS  REQUIREMENTS

9. EQUIPMENTs  REQUIREMENTs

10. WASTE MANAGEMENT

11. SPECIAL CONTROL MEASURES.

12. SUPPORTING  DOCUMENTATION

13. DISTRIBUTION

1.SCOPE

Ø  This procedure to clear the method of the supply, installations of Electrical PVC Conduits for the project.

Ø  This document details Electrical PVC Conduits Installation:

1.  Preparation of work.

2.  Delivery and inspection upon arrival of material at site.

3.  Installation of the system.

2. definitions

           PQP             : Project Quality Plan

PSP              : Project Safety Plan

QCP             : Quality Control Procedure

HSE             : Health, Safety and Environment

MS               : Method Statement

ITP               : Inspection Test Plan

QA/QC         : Quality Assurance / Quality Control Engineer.

WIR              : Inspection and Test Request

MIR              : Material Verification Record.

3. HEALTH  AND  SAFETY

Ø  Strictly followed as per the manufacturer's Health and Safety recommendations for handling and use of the materials.

Ø  Ensure all involved personnel shall be aware of the same.

Ø  Specific safety measures have to follow as applicable, and all the safety measures are covered separately in the project safety plan.

4. OPERATION

Ø  Material: 

·       Material used will be as approved by the Engineer.

·       The sizes and routes routing will be as per the approved Shop Drawings.

Ø  Storage and Protection: 

·       Deliver components parts to site, completely identified in accordance with shop and certified CAD Drawings prepared for this work.

·       Store in accordance with the manufacturer’s instructions, above ground, properly protected from the weather and construction activities.

5. INSTALLATION  and  fixation

Ø  Pre-Installation:

·       All materials and documentation relevant to this particular section of works will be checked and verified ensuring that  these are correct and approved type.

 

·       Prior to the commencement of works, ensure that the areas for permanent installation are ready, accessible and in suitable condition.

Ø  Installation:

·       During the course of the installation of the conduit system, procedures for working and dressing the installation as recommended shall be employed.

·       All bends and sets shall be in accordance with IEE regulation 522-08 formed with the aid of a helical spring fitted internally, with if necessary, the conduit warmed sufficiently for it to move without avoidable wall thinning of the out side of the bend.

·       Conduit system shall be installed so as to ensure compliance with the requirements of Specified Standard and Regulation.

·       Joints between PVC conduit + fittings shall be made with suitable adhesive, but expansion couplings shall be installed where any length of conduit , inclusive of draw in boxes etc, exceeds five meters in length.

·       The minimum and maximum sizes of conduit to be employed shall be 20mm and 32mm diameter respectively, unless otherwise stated in subsequent sections of the Specification .

·       Conduits in floors shall be routed and installed so as to avoid the fixings of floor standing equipment to be installed on the floor.

 

Ø  Commissioning:

·       When conduits are run on shuttering, prior to the laying of concrete insitu, additional security must be provided near to every box and at intervals of not more than 1.2 meters by binding short lengths of steel wire, of not less than 2mm diameter twisted around the conduit and reinforcing steel. The conduits shall be adequately fixed to prevent excessive movement and damage during the pouring and setting of concrete and shall be protected from mechanical damage. Check there is no damage before screed / concrete is poured. Unless otherwise indicated to cast in conduits shall not be less than 30mm.cores to plastered over conduits shall not be less than 5mm.

·       Where conduits are left "open ended" prior to wiring they shall be protected by caps or plugs to prevent the ingress of building material.

·       All conduits runs must be designed to permit wiring to be readily installed after the complete erection of the conduits through the available draw-in, accessory and luminary suspension boxes.

·       Where surface mounted equipment (other than luminaries) is specified, all concealed conduits shall be terminated and an adaptable box installed recessed into the wall at every surface mounted equipment position.

·       Where conduits pass through an external wall/roof the conduit box shall be fitted on the side and after wiring filled with an inert, permanently plastic compound having a high insulation value.

·       Make provision in conduit and trunking, installation where building expansion joints are crossed or settlement is likely

·       Ensure conduits are not concealed until works has been inspected and approved. Ensure that conduit and fittings buried in concrete or behind plaster are protected against corrosion or electrolytic action prior to rendering.

Ø  Technical Assistance:

·       The installation supervising technician for the system trade shall instruct the CONSULTANT Engineer, and Construction Site Manager on the programming and correct operation of the system after the installation is completed.

·       This instruction shall be scheduled at the convenience of the staff.

·       All such instruction shall be properly recorded.

·       WIR will be issued for Consultant approval upon making sure that the installation of the system equipment’s done as per approved shop drawings and specs and manufacturer recommendations.

6. RESPONSIBILITIES

Ø  PROJECT MANAGER

1.     To ensure that all the preparation and application works are carried out according to the Contract Specification and with the approved drawings.

2.     To ensure that the progressing of works is carried out according to the planned program and as per the approved method of statement.

3.     To ensure that all the equipment and material required executing the work are available according to the planned construction program.

4.     To co-ordinate with the Main contractor, MEP coordinator, Safety Officer for a safe and proper execution of the works.

Ø  SITE ENGINEER

1.     To ensure that the works are carried out according to the Contract Specification, approved method statement and the shop drawings.

2.     To provide all necessary information and distribute responsibilities to his construction.

3.     To monitor the progress of work in relation with the work program and to report to the Project Manager.

4.     To co-ordinate with the safety officer and to ensure that the works are carried out in safe practicing method.

Ø  FOREMAN

1.     The foreman will carry out his duties by maintaining continuous coordination with the site engineer on daily basis, and ensure proper distribution of the work force on the required and planned locations.

2.     To ensure that his assistant foreman/ charge hand are aware of the job requirements and they have enough information to carry out their duties properly.

3.     To ensure that the daily work is progressing as planned and advice the site engineer of any requirement for additional resources.

4.     To ensure in consultation with the site engineer that the manpower involved in the works are moving as agreed and planned for the work.

5.     To control disposal of waste materials according to the instructions received from the site engineer.

6.     To ensure full coordination with the safety officer to maintain safe working and proper house keeping of the site, following the proved safety measures and further ensure that all his working team are aware of the same to prevent accident and losses.

7.     To inform the site engineer regarding areas ready for inspection.

8.     Foreman and the storekeeper are responsible for the distribution and control of materials.

Ø  SAFETY ENGINEER

1.     Ensure the implementation of all the safety measures in accordance with the HSE plan and everybody aware of it for it’s proper implementation.

2.     Ensure all the implemented safety measures are adequate to maintain safe working on the site.

3.     Inspect all the site activities and train the person to prevent accidents and it’s proper implementation.

4.     Ensure that the site is maintained clean and tidy.

Ø  TECHNICIAN FROM SUPPILER

1.     The carrying-out of work and the proper distribution of all the available resources in coordination with the sub-contractor Site Engineer on a daily basis.

2.     Daily reports of the works are achieved and coordinated for the future planning with the Site Engineer.

3.     Complying with the sub-contractor basic design practices, particularly those related to safety and engineering

4.     Meeting with any type of unforeseen incident or requirement and reporting the same to the Site Engineer immediately.

Ø  STORE KEEPER

1.     Responsible for overall Store operations in making sure to store the material delivery to the site and keep it in suitable area that will keep the material in safe from rusty and damage.

2.     One who will acknowledge the receiving of materials at site in coordination with QA/QC and concerned Engineer.

7. MANPOWER  REQUIRED

Ø  Charge hand and Experienced Technicians

8. MATERIALS  REQUIREMENTS

Ø  Electrical PVC Conduits Components and Accessories

9. EQUIPMENTs  REQUIREMENTs

Ø  The Equipment that will be engaged for Electrical PVC Conduits  Installation will be as follows:

1.     Hack saw

2.     Measuring tape

3.     Cutting plier

4.     Knipex (End cutter)

5.     Bending spring

6.     Drilling Machine

10. WASTE MANAGEMENT

Ø  The Rubbish which would be created from our scope of works will be disposed to the designated dumping ground.

11. SPECIAL CONTROL MEASURES

Ø  The following general control measures against Safety, Environment and Quality shall be required for our scope of work and special control measures are not applicable for us :

·         Proper PPE must be worn at all time

·         Permit to work at height > 2m where applicable

·         Lifting operation permit (using crane) where applicable.

·         Confined space permit where applicable.

·         Approved work method statement and risk assessment will be made available to site.

·         All workers doing the work shall be briefed on this method statement and risk assessment.

12. SUPPORTING  DOCUMENTATION

Ø  This method Statement should be read in conjunction with the below referenced documentations:

  • ITP for Anti – termite Treatment.
  • Insulation Resistance and continuity Test Report.

13. DISTRIBUTION

Ø  Copy of this method statement shall be issued to the following for information / action / comments:

  1. Project Manager
  2. Site Engineer
  3. Foremen
  4. Safety Engineer
  5. Technician From Supplier
  6. Store Keeper