METHOD STATEMENT FOR PVC CONDUITS INSTALLATION
Ø TABLE OF CONTENTS
1. SCOPE
2. definitions
3. HEALTH AND SAFETY
4. OPERATION
5. installation and fixation
6. RESPONSIBILITIES
7. MANPOWER REQUIRED
8. MATERIALS
REQUIREMENTS
9. EQUIPMENTs
REQUIREMENTs
10. WASTE MANAGEMENT
11. SPECIAL
CONTROL MEASURES.
12. SUPPORTING
DOCUMENTATION
13. DISTRIBUTION
1.SCOPE
Ø This procedure to clear the method of the supply, installations of Electrical PVC Conduits for the
project.
Ø This document details Electrical PVC Conduits Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. definitions
PQP : Project Quality Plan
PSP : Project Safety Plan
QCP : Quality Control Procedure
HSE : Health, Safety and Environment
MS : Method Statement
ITP : Inspection Test Plan
QA/QC : Quality Assurance / Quality Control
Engineer.
WIR : Inspection and Test Request
MIR : Material Verification Record.
3. HEALTH
AND SAFETY
Ø Strictly followed as per the manufacturer's Health
and Safety recommendations for handling and use of the materials.
Ø Ensure all involved personnel shall be aware of the
same.
Ø Specific safety measures have to follow as applicable, and all the
safety measures are covered separately in the project safety plan.
4. OPERATION
Ø Material:
·
Material used will be as
approved by the Engineer.
·
The sizes and routes routing
will be as per the approved Shop Drawings.
Ø Storage and Protection:
·
Deliver components parts to
site, completely identified in accordance with shop and certified CAD Drawings prepared for this work.
·
Store in accordance with the
manufacturer’s instructions, above ground, properly protected from the weather
and construction activities.
5. INSTALLATION
and fixation
Ø Pre-Installation:
· All
materials and documentation relevant to this particular section of works will
be checked and verified ensuring that
these are correct and approved type.
· Prior
to the commencement of works, ensure that the areas for permanent installation
are ready, accessible and in suitable condition.
Ø Installation:
· During the
course of the installation of the conduit system, procedures for working and
dressing the installation as recommended shall be employed.
· All bends
and sets shall be in accordance with IEE regulation 522-08 formed with the aid
of a helical spring fitted internally, with if necessary, the conduit warmed
sufficiently for it to move without avoidable wall thinning of the out side of
the bend.
· Conduit
system shall be installed so as to ensure compliance with the requirements of
Specified Standard and Regulation.
· Joints
between PVC conduit + fittings shall be made with suitable adhesive, but
expansion couplings shall be installed where any length of conduit , inclusive
of draw in boxes etc, exceeds five meters in length.
· The
minimum and maximum sizes of conduit to be employed shall be 20mm and
32mm diameter respectively, unless otherwise stated in subsequent sections of
the Specification .
· Conduits
in floors shall be routed and installed so as to avoid the fixings of floor
standing equipment to be installed on the floor.
Ø Commissioning:
· Where
conduits are left "open ended" prior to wiring they shall be
protected by caps or plugs to prevent the ingress of building material.
· Where surface mounted equipment (other than luminaries) is specified, all concealed conduits shall be terminated and an adaptable box installed recessed into the wall at every surface mounted equipment position.
· Where conduits pass through an external wall/roof the conduit box shall be fitted on the side and after wiring filled with an inert, permanently plastic compound having a high insulation value.
· Make provision in conduit and trunking, installation where building expansion joints are crossed or settlement is likely
· Ensure conduits are not concealed until works has been inspected and approved. Ensure that conduit and fittings buried in concrete or behind plaster are protected against corrosion or electrolytic action prior to rendering.
Ø Technical Assistance:
· The installation supervising technician for the system trade shall
instruct the CONSULTANT Engineer, and Construction Site Manager on the
programming and correct operation of the system after the installation is
completed.
· This instruction shall be scheduled at the convenience of the
staff.
· All such instruction shall be properly recorded.
· WIR will be issued for Consultant approval upon making sure that
the installation of the system equipment’s done as per approved shop drawings
and specs and manufacturer recommendations.
6. RESPONSIBILITIES
Ø PROJECT
MANAGER
1. To ensure that all the preparation and
application works are carried out according to the Contract Specification and
with the approved drawings.
2. To ensure that the progressing of works
is carried out according to the planned program and as per the approved method
of statement.
3. To ensure that all the equipment and
material required executing the work are available according to the planned
construction program.
4. To co-ordinate with the Main contractor, MEP coordinator, Safety Officer for a safe and proper execution of the works.
Ø SITE
ENGINEER
1. To ensure that the works are carried out
according to the Contract Specification, approved method statement and the shop
drawings.
2. To provide all necessary information and
distribute responsibilities to his construction.
3. To monitor the progress of work in
relation with the work program and to report to the Project Manager.
4. To co-ordinate with the safety officer
and to ensure that the works are carried out in safe practicing method.
Ø FOREMAN
1. The foreman will carry out his duties by
maintaining continuous coordination with the site engineer on daily basis, and
ensure proper distribution of the work force on the required and planned
locations.
2. To ensure that his assistant foreman/
charge hand are aware of the job requirements and they have enough information
to carry out their duties properly.
3. To ensure that the daily work is
progressing as planned and advice the site engineer of any requirement for
additional resources.
4. To ensure in consultation with the site
engineer that the manpower involved in the works are moving as agreed and
planned for the work.
5. To control disposal of waste materials
according to the instructions received from the site engineer.
6. To ensure full coordination with the
safety officer to maintain safe working and proper house keeping of the site,
following the proved safety measures and further ensure that all his working
team are aware of the same to prevent accident and losses.
7. To inform the site engineer regarding
areas ready for inspection.
8. Foreman and the storekeeper are
responsible for the distribution and control of materials.
Ø
SAFETY ENGINEER
1.
Ensure the
implementation of all the safety measures in accordance with the HSE plan and
everybody aware of it for it’s proper implementation.
2.
Ensure all
the implemented safety measures are adequate to maintain safe working on the
site.
3.
Inspect
all the site activities and train the person to prevent accidents and it’s
proper implementation.
4.
Ensure
that the site is maintained clean and tidy.
Ø
TECHNICIAN FROM SUPPILER
1.
The
carrying-out of work and the proper distribution of all the available resources
in coordination with the sub-contractor Site Engineer on a daily basis.
2.
Daily
reports of the works are achieved and coordinated for the future planning with
the Site Engineer.
3.
Complying with
the sub-contractor basic design practices, particularly those related to safety
and engineering
4.
Meeting
with any type of unforeseen incident or requirement and reporting the same to
the Site Engineer immediately.
Ø
STORE KEEPER
1. Responsible for overall Store
operations in making sure to store the material delivery to the site and keep
it in suitable area that will keep the material in safe from rusty and damage.
2. One who will acknowledge the
receiving of materials at site in coordination with QA/QC and concerned
Engineer.
7. MANPOWER REQUIRED
Ø Charge hand and Experienced Technicians
8. MATERIALS
REQUIREMENTS
Ø Electrical PVC Conduits Components and Accessories
9. EQUIPMENTs
REQUIREMENTs
Ø The Equipment that will be engaged for Electrical PVC Conduits Installation will be as follows:
1.
Hack saw
2.
Measuring tape
3.
Cutting plier
4.
Knipex (End cutter)
5.
Bending spring
6.
Drilling Machine
10. WASTE MANAGEMENT
Ø The Rubbish which would be created from our scope of works will be disposed to the designated dumping ground.
11. SPECIAL CONTROL MEASURES
Ø The
following general control measures against Safety, Environment and Quality
shall be required for our scope of work and special control measures are not
applicable for us :
·
Proper PPE must be worn at all
time
·
Permit to work at height >
2m where applicable
·
Lifting operation permit
(using crane) where applicable.
·
Confined space permit where
applicable.
·
Approved work method statement
and risk assessment will be made available to site.
·
All workers doing the work
shall be briefed on this method statement and risk assessment.
12. SUPPORTING
DOCUMENTATION
Ø This method Statement should be read in conjunction with the below
referenced documentations:
- ITP
for Anti – termite Treatment.
- Insulation
Resistance and continuity Test Report.
13. DISTRIBUTION
Ø Copy of this method statement shall be issued to the following for
information / action / comments:
- Project
Manager
- Site
Engineer
- Foremen
- Safety
Engineer
- Technician
From Supplier
- Store Keeper
4 comments:
Awesome Post! I appreciate you sharing. Swiftit.ae, one of the top CCTV installation companies in Abu Dhabi, where they offer excellent software for your IT administration. You could think about looking them up.
Awesome Post! I appreciate you sharing. Swiftit.ae, one of the top CCTV installation companies in Abu Dhabi, where they offer excellent software for your IT administration. You could think about looking them up.
Thank you for sharing Knowledgeable information with us.And if you are searching an Online MBA DEGREE COURSE from Top Universities in India.
if u want more information plz click link below:
Online MBA
Online MBA Courses
Online MBA Degree
Online MBA In General Management
Online MBA In Finance
Online MBA In Human Resource Management
Online MBA In IT Management
Online MBA In Marketing
Online MBA In Logistics and Supply Chain Management
Looking for a reliable and durable armoured cables for your industrial needs? Discover the Steel Wire Armoured Cable BS 7846 MGT! Engineered for high performance and safety, this cable meets stringent British Standards (BS 7846) and is ideal for heavy-duty applications. Whether you're in construction, power distribution, or any industry requiring robust cabling solutions, this product ensures reliability and safety.
Post a Comment